Asphalt topping is complete throughout the golf village and villa parking lots.
1.aspx?width=400&height=200)
Scoreboard foundations and stone has begun on the outside of the Golf Shop. Inside of the buildings, the Golf Shop countertops and millwork have been installed as well as the final items of bathroom accessories.

Touch up painting has begun throughout the building. In the Restaurant, equipment tie-in is ongoing as paint nears completion in the main dining area. In both buildings, flooring has been installed throughout.
Click here for a walk through video of the two buildings.
The next weeks will bring the buildings near completion and we look forward to the progress that will be made.