Through all of the rain, Brasfield & Gorrie has actually managed to complete a few projects with the help of the tent. The prep for the Golf Shop haul-in has been completed and the haul-in is set to start soon.
We are currently waiting for the weather to clear so the wood framing of the Pool Cabana can begin. The trusses are in fabrication and the Cabana trusses are set to be delievered soon in order to begin. Brasfield & Gorrie really need a solid week of no rain in order to continue on the Cabana.
The Restaurant plumbing rough-in has been completed, again with help to the large tent. The restaurant foundations should begin soon, with hopes the weather is in our favor.
Thank you for following our progress!