There have been some noticeable changes that continue on the exterior of the building as we have wrapped up siding and stone activities.
(Pictured above: The Golf Shop birdseye view from new Bag Drop)
Paint prep has begun and we should see exterior paint beginning on buildings this week.
(Pictured above: birdseye view from the lake)
Around the site, finish grading is nearing completion to allow for landscape planting to begin. Drywall still remains the major activity inside of the building’s as we continue to hang and finish.
(Pictured above: new fire pit in between the Restaurant and Golf Shop)