This past week brought a lot of progress to the project. Major milestones accomplished this week were our Pro Shop slab pour, Restaurant framing, and curb & gutter starting.

Click title for the full update.

Read More

3/18/2020 2:11:22 PM

March 18, 2020

We were lucky with mostly good weather last week which allowed us to get a lot done, one major was hitting the slab pour milestone for the Restaurant.
Click title for full post.
 

Read More

3/11/2020 11:57:24 AM

March 11, 2020

The sun has reappeared and Brasfield & Gorrie were able to push while we had good weather.

Click the title for the full update.

Read More

3/5/2020 2:07:56 PM

March 5, 2020

The Golf Shop pad haul in has been completed and the main storm line through the parking lot is completed as well. The overall Storm System is approximately 85% complete.